Essential drainage repair works are due to commence at the above location on Saturday 14th February for a period of up to 8 days between the hours of 08:00 – 18:00. The scheme requires excavation within the carriageway to remedy the numerous collapses and blockages of the existing drainage network. To minimise disruption as best possible, the works are to be undertaken in phased sections during the school holidays as listed below and on the drawing attached. There will also be the introduction of new gullies in areas that currently experience standing water.
The programme of works for the drainage works are as follows;
Sat 14th Feb & Sun 15th – Athelstane Crescent to Sherwood Avenue.
Mon 16th Feb to Wed 18th – Thorne Road to Athelstane. Crescent
Thurs 19th Feb – Milton Grove to St Oswalds Drive.
Fri 20th Feb – Church Balk Gardens to St Oswalds Drive.
Sat 21st Feb – Church Balk Gardens to Scott Crescent.
Sun 22nd Feb – Doncaster Road to Church Croft.
Resurfacing of Church Balk will now take place in the Easter Holidays.